A footing takeoff turns a set of foundation drawings into a list of bars you can order. Done well, it tells you how many feet of each bar size you need, how much the steel weighs, and how many stock bars to buy. Done badly, it leaves a crew standing in an open trench waiting on a second delivery. This guide walks through the method for continuous footings, spread footings and grade beams, with worked examples you can follow on paper or check with the Chandler Reinforcing Steel rebar calculator.
Every number in the examples is hypothetical. Your structural drawings, general notes and engineer of record control bar sizes, spacing, cover, lap lengths and hook details. This guide helps you count and total what the drawings already specify. It does not design anything.
Why Footings Deserve Their Own Takeoff
Slabs are mostly repetition: the same bar at the same spacing across an area. Footings are different. A foundation plan mixes continuous strip footings, isolated pads, stem walls, grade beams and dowels, and each one is reinforced differently. Corners, intersections and steps in the footing add pieces that a simple area calculation never finds.
Because footing steel is buried and inspected before the pour, mistakes are also expensive. A short order means a stalled inspection or a rushed second delivery. An oversized order means waste you paid for. The goal of the takeoff is a count you can defend line by line.
Start With the Drawings, Not the Calculator
Before you calculate anything, collect these items from the plans and specifications:
- Footing schedule, with the width, depth and mark of each footing type
- Bar sizes and the number of continuous bars in each footing
- Spacing for any transverse or mat bars
- Clear cover, usually measured from the bar to the soil or form face
- Lap splice length, stated in bar diameters or inches
- Hook and bend requirements, including corner bars and dowels
- Stem wall and column dowel sizes, spacing and projection
- Where footings step, intersect or change width
If a detail is missing, ask before you guess. A one-line question to the detailer costs less than re-cutting bars.
Using the Rebar Calculator for Footings
The site calculator handles the arithmetic once you have the inputs. Open the Rebar Calculator page and accept the terms to unlock it. Use Part A (linear feet) when you already know the run length of each bar, which is the usual case for continuous footings and grade beams. Use Part B (area) for pad footings and mats where bar count depends on spacing.
For each row you enter a bar size, a length and a quantity. Optional settings add lap splices and hooks, and the stock bar length is an editable setting that defaults to 20 feet. The results show linear feet, pounds and tons, and you can send the summary with your quote request.
The calculator does not read drawings, check structural adequacy or choose bar sizes. Treat its output as an estimate and confirm quantities against your drawings and any shop drawings before you order.
Run Your Numbers
Total your linear feet and weight in pounds and tons with the Chandler Reinforcing Steel Rebar Calculator.
Open the Rebar CalculatorKnow the Terms
- Continuous footing: a strip footing that runs under a wall, with bars running its full length.
- Spread footing or pad: an isolated footing under a column, usually reinforced with a bar mat.
- Grade beam: a reinforced concrete beam at or near grade, often with top and bottom bars and stirrups.
- Stem wall: a short wall rising from a footing, tied in with dowels or vertical bars.
- Dowel: a bar that starts in one pour and projects into the next to connect the two.
- Lap splice: an overlap where two bars are joined along their length.
- Clear cover: the concrete between the bar surface and the nearest face of the pour.
- Stock length: the standard length of bar delivered before cutting. A 20 ft bar is a common planning length.
The Formulas
You need only a handful of relationships. The letters used below are defined after the table.
| What you are finding | Formula |
|---|---|
| Bars in a mat, one direction | ⌈(D − 2e) ÷ s⌉ + 1 |
| Centerline offset from clear cover | e = c + (db ÷ 2) |
| Number of splices in one run | ⌈R ÷ S⌉ − 1 |
| Lap length from bar diameters | ℓ = n × db |
| Total length of a continuous bar | R + (splices × ℓ) |
| Weight | Total length × weight per foot |
| Stirrups along a beam | ⌈L ÷ s⌉ + 1 |
| Fewest possible stock bars | ⌈Total length ÷ S⌉ |
In these formulas, D is the footing dimension the bars are spread across, e is the offset from the edge to the first bar centerline, s is the spacing, c is clear cover, db is the bar diameter, R is the run length of one bar, S is the stock bar length, n is the lap length in bar diameters and L is the beam length. The ceiling symbol ⌈ ⌉ means round up to the next whole number. Always round up, because a fraction of a space still needs a bar.
Weight per foot for common bars: #3 is 0.376 lb, #4 is 0.668 lb, #5 is 1.043 lb, #6 is 1.502 lb, #7 is 2.044 lb and #8 is 2.670 lb. Tons here are US short tons, which are 2,000 pounds.
Step 1: Measure the Run of Each Continuous Bar
For strip footings, measure along the footing centerline on the plan, not along the outside edge. The two differ by half the footing width at every corner, and on a closed perimeter that difference adds up. Record one run length per footing mark. If the footing steps or changes width, break it into separate runs so each has its own bar count and size.
Step 2: Add Lap Splices
Footing runs are often longer than one stock bar. Count a splice each time a run goes past the stock length: splices = ⌈R ÷ S⌉ − 1. Multiply by the lap length from the drawings and add the result to the run. If the drawings give the lap in bar diameters, multiply by the bar diameter. A #5 bar has a diameter of 5/8 in, so 40 bar diameters is 25 in, or about 2.08 ft.
Large bars, usually #14 and #18, are typically joined with mechanical splices instead of laps. Follow the drawings.
Step 3: Handle Corners and Intersections
Continuous bars do not turn corners by themselves. Drawings normally call for corner bars, sometimes called L-bars, at each corner and at wall intersections so the steel stays continuous. Count them as separate pieces: one per bar per corner, each with the leg lengths and hooks the detail shows. This is the most commonly missed item in footing takeoffs, so build a short corner list as you go.
Step 4: Count Mats, Stirrups and Dowels
For pad footings, use the bar count formula once for each direction. For grade beams, count stirrups along the length with ⌈L ÷ s⌉ + 1, then multiply by the cut length from the bend schedule. For stem walls, count dowels at their spacing along the wall and add the length of the dowel in the footing, the projection and any hook.
Step 5: Total, Weigh and Turn Footage Into an Order
Add the lengths for each bar size separately, because you order and price by size. Multiply each total by the weight per foot, then add a waste allowance if your company uses one. Finally divide by stock length and round up. That gives the fewest stock bars, but cutting layout can push the real number higher, as Example 2 shows.
Three Worked Examples
Example 1: A Continuous Footing With Lap Splices
Assumptions:
- Closed rectangular footing, centerline perimeter of 134 ft read from the plan
- Two continuous #5 bars (hypothetical)
- Lap length of 40 bar diameters
- Stock length of 20 ft
- Run length per bar: 134 ft
- Splices per bar: ⌈134 ÷ 20⌉ − 1 = 7 − 1 = 6
- Lap length: 40 × 0.625 in = 25 in = 2.083 ft
- Lap footage per bar: 6 × 2.083 = 12.5 ft
- Length per bar with laps: 134 + 12.5 = 146.5 ft
- Total for two bars: 293 ft
- Weight: 293 × 1.043 = 305.6 lb, or about 0.15 ton
- Fewest stock bars: ⌈293 ÷ 20⌉ = 15
This count covers the continuous bars only. Corner bars, dowels and any extra steel at openings are separate lines on the takeoff.
Example 2: Pad Footings and Why Cut Layout Matters
Assumptions:
- Eight pads, each 6 ft by 6 ft
- #5 bars each way, hypothetical maximum spacing of 12 in
- Clear cover of 3 in, so e = 3 + 0.3125 = 3.3125 in, or 0.276 ft
- Bar cut length of 5.5 ft (6 ft less 3 in of cover at each end)
- Stock length of 20 ft
- Usable width: 6 − (2 × 0.276) = 5.448 ft = 65.4 in
- Bars each way: ⌈65.4 ÷ 12⌉ + 1 = 6 + 1 = 7
- Bars per pad: 7 × 2 = 14
- Footage per pad: 14 × 5.5 = 77 ft
- Footage for eight pads: 616 ft
- Weight: 616 × 1.043 = 642.5 lb
- Footage method: ⌈616 ÷ 20⌉ = 31 stock bars
- Cut layout: each 20 ft bar yields three 5.5 ft pieces (16.5 ft used, 3.5 ft left over). The job needs 8 × 14 = 112 pieces, and ⌈112 ÷ 3⌉ = 38 stock bars.
The footage method suggests 31 bars, but the cut layout needs 38. Short offcuts of 3.5 ft usually cannot be used elsewhere, so the second number is the one to plan around unless you have a use for the leftovers.
Example 3: A Grade Beam With Stirrups
Assumptions:
- Beam length of 40 ft, 12 in wide by 18 in deep
- Three #5 bars top and three #5 bars bottom, continuous
- #3 stirrups at 12 in spacing
- Stirrup cut length of 62 in from the bend schedule (hypothetical)
- Lap length of 40 bar diameters, stock length of 20 ft
- Longitudinal bars: 6 × 40 = 240 ft
- Splices per bar: ⌈40 ÷ 20⌉ − 1 = 1, with a lap of 2.083 ft
- Lap footage: 6 × 2.083 = 12.5 ft
- Total #5 length: 252.5 ft, or 263.4 lb
- Stirrups: ⌈480 in ÷ 12 in⌉ + 1 = 41
- Stirrup footage: 41 × 62 in = 2,542 in = 211.8 ft
- Weight at 0.376 lb per foot: 79.6 lb
Beam total: about 343.0 lb, or roughly 0.17 ton
Notice that the stirrups are a small share of the weight but take most of the fabrication effort. That is why bend schedules matter: a bent bar is quoted and prepared differently from a straight one.
What Often Goes Wrong
- Measuring along the outside edge of a footing instead of the centerline
- Forgetting corner bars and intersection bars
- Counting dowels in the stem wall quantity but not in the footing quantity
- Ignoring laps because a run looks like it fits in one bar
- Mixing bar sizes in one total
- Using area shortcuts on a footing that needs a real bar schedule
- Ordering from an old revision of the drawings
A second person checking the takeoff against the plan catches most of these.
Cover, Spacing and Placement in the Field
The takeoff assumes the steel can be placed as drawn. In the field, bars are held off the soil with chairs or concrete blocks, tied at intersections and kept away from the form faces. Tie wire, chairs and spacers are part of the real cost of a footing, so add them to your list. Reinforcing accessories are stocked, and other accessories can be sourced on request and quoted with your order.
The pour schedule and the inspection schedule decide when the steel should arrive. Confirm the delivery window and where the truck can unload before the date, not the morning of the pour.
Send the Takeoff for a Quote
When you have totals, send them with the drawings for a written quote. Include:
- Structural drawings and specifications
- Your takeoff or bar schedule, if you have one
- Project address
- Bid deadline
- Required delivery date
Chandler Reinforcing Steel is a supply and install company. We stock rebar, cut and bend to your schedule, deliver pre-tied cages and quote installation by project. We submit shop drawings to the engineer of record for approval, and revision pricing is quoted if a contract is awarded. Our office is at 3100 West Ray Road, Suite 201-A, Chandler, AZ 85226. Pickup is not offered, and delivery is confirmed by project address across Chandler, Phoenix, Mesa and Tucson.
Frequently Asked Questions
How do I know how many bars a footing needs?
The footing schedule on your structural drawings gives the bar size and count. If it describes a mat, count bars with ⌈(D − 2e) ÷ s⌉ + 1 in each direction.
Do I measure to the outside of the footing or the centerline?
Use the centerline of the footing for continuous bars, then add corner bars and laps as the drawings show.
How do I figure lap splices?
Count one splice each time a run passes the stock length, then multiply by the lap length on the drawings.
Why does my stock bar count differ from my footage divided by 20?
Cutting layout leaves offcuts. When pieces are short, several fit in a bar but a remainder is wasted. Count pieces per stock bar, not just footage.
Does the calculator replace an engineer or a bar schedule?
No. It is an estimating aid. Your drawings and engineer of record control quantities and details.
Can you cut, bend and install the steel too?
Yes. We cut and bend bars #3 through #18 from your schedule, and installation is quoted by project.
Reinforcing steel quantities, lead times and pricing depend on the project, so they are quoted individually. Use the calculator for a first estimate, confirm it against your drawings, and send both with your quote request.